Quantum Expert Report, Belgium
TSA Riley was appointed as quantum expert on behalf of a tier 1 international contractor in an arbitration on a data centre in Belgium against the Employer.

Data centre, London, UK
TSA Riley was appointed as both quantum and delay experts on behalf of an owner in an adjudication against a contractor on a data centre in London.

Quantum Expert ReportData centre, Belgium
TSA Riley was appointed as quantum expert on behalf of a tier 1 international contractor in an arbitration on a data centre in Belgium defending claims from the subcontrator.

Quantum Expert Report, Netherlands
TSA Riley was appointed as quantum expert on behalf of a tier 1 international contractor in anticipation of arbitration proceedings on a data centre in the Netherlands.

Delay Claims Support, Dublin, Ireland
TSA Riley provided contractual advice in relation to the notification and assessment of delay events, together with support in preparing evidence of costs incurred and how such costs were directly linked to the individual delay events notified.

Extension of Time Report, Netherlands
TSA  Riely was appointed on behalf of an international M&E subcontractor to conduct a detailed ‘Windows Analysis’ supported with contemporaneous evidence, to determine exactly what delays a 6MW data centre COLO project faced, when the delays occurred and the impact the delays had on achieving Ready for Service (RFS date).

Contractual and Delay Advice, Netherlands
TSA Riely was appointed on behalf of a Tier 1 international contractor to support during the fitout of a 4.5MW data centre, by assisting with raising timely notices alongside supporting delay substantiation.

Extension of Time (EOT) Report, Spain
TSA Riley was appointed on behalf of a large M&E subcontractor to review the delays across a 9.4MW COLO data centre project and substantiate an entitlement for an EOT. Following the completion of the report, we were further instructed to complete a close out programme for the remaining scope of work.